Oracle issues force majeure notice for New Mexico Stargate data center

Oracle has sent a force majeure notice related to its Stargate data center in New Mexico. The notice could allow the company to delay payments if the facility does not come online by its 2028 target.

Sylvester Eyamah

By Sylvester Eyamah

Sep 25, 2026, 4:58 AM  ·  3 min read

Oracle issues force majeure notice for New Mexico Stargate data center
Oracle issues force majeure notice for New Mexico Stargate data center — Technology

Oracle has sent a force majeure notice to the developer of its massive New Mexico data center project, a move designed to shield the company from mounting expenses if the site fails to meet its 2028 operational target .

What Oracle is trying to do

The notice went to a unit of Blue Owl Capital, which owns the project's developer, Stack Infrastructure. Rather than walking away as the site's main tenant, Oracle is seeking the right to defer payments if the data center, dubbed "Project Jupiter," gets derailed and misses its planned 2028 opening .

Companies typically invoke force majeure to free themselves from contractual obligations when problems arise beyond their control. In this case, Oracle is asserting its contractual position ahead of potential construction delays. It remains uncertain whether such a maneuver would legally release Oracle from its previously agreed financial obligations .

"Project Jupiter remains on our planned schedule," an Oracle spokesperson said. "We are fully committed to New Mexico and confident in our path forward."

What's gone wrong

The 1,400-acre campus in Doña Ana County is designed to handle 2.45 gigawatts, enough electricity to power roughly 1.8 million homes at any given moment .

The biggest issue is energy. A 17.8-mile natural gas pipeline that was supposed to begin service this month and supply fuel to the site was instead delayed by nearly six months to February 1, 2027, following repeated permit denials from the New Mexico State Land Office . The project is designed to be powered by gas-powered fuel cells from Bloom Energy.

The project has also faced stiff local opposition. A recent poll found 65% of New Mexico residents opposed to data center construction in the state . The campus has become a political flashpoint ahead of the U.S. midterm elections .

The financial stakes

A group of about 20 banks provided an $18 billion loan to fund construction, one of several mega-debt deals bankrolling the AI infrastructure boom . The debt tied to the development is already trading at stressed levels, below 90 cents on the dollar .

The project is part of Stargate, the $500 billion AI infrastructure initiative involving OpenAI, SoftBank, and Oracle . OpenAI signed a $400 billion deal with Oracle and SoftBank to support the development of five U.S. data centers including the New Mexico site .

Oracle's shares fell around 4% following the news .

What I think

This story captures a tension that's going to define the next few years of AI infrastructure. The ambitions are enormous. The money is committed. But the physical realities of power, permitting, and local resistance don't move at the speed of a term sheet.

What stands out to me is that Oracle isn't trying to exit. It's trying to protect itself. That tells you the company still believes in the project, but it's also acknowledging that the timeline is genuinely at risk. Force majeure is usually reserved for hurricanes and wars. Using it here, even precautionarily, signals that Oracle sees the regulatory and logistical hurdles as beyond its control.

The stressed debt trading is the part worth watching. If lenders start losing confidence in these mega-projects, the cost of capital for the entire AI buildout could rise. Oracle is in a more tenuous cash position than its larger peers, which makes it more sensitive to these kinds of disruptions .

The deeper question is whether the AI industry's aggressive timelines can survive contact with the real world. Permits take time. Pipelines need approval. Communities push back. None of that fits neatly into a 2028 deadline. Oracle may be the first to formally acknowledge that gap, but it probably won't be the last.